Project Overview

The refurbishment of a fixed wing office building and provision of new simulators, training, and operations facilities. The Rotary Wing project required the design and construction of a new two-storey office block and refurbishment of an existing aircraft hangar.

We took on the challenge of working on two separate projects simultaneously, on a live site which required us to cross the runway that runs through the site. The Rotary and Fixed Wing buildings required state-of-the-art specialist facilities and equipment, along with spaces suitable for briefings, operation and mission control.

RAF Valley – Rotary Wing They said...

I have had the pleasure of working with Steve & his team on several schemes. Communication is always superb and the team embrace a fully collaborative approach, do an excellent job and always deliver on schedule.

Daniel Hampson, Project Manager,
Design

The design was developed by Kier and METSEC taking into consideration the buildings had to withstand the corrosive effects of sea-spray and salt due to geographical position.

Once finalised the deigns were subsequently costed and the project delivered by Optimal.